Construction of the new Wondersmith Studio and HQ is complete! 🎉

See photos below and on Instagram.

  • Located in a 200-year-old post-and-beam barn on 1.8 acres near Acton Historic Center

  • Just minutes from Route 2 and Concord; 25 minutes to Cambridge

  • Features:

    • Antique heart pine floors & original chestnut beams

    • Panoramic natural light and 20′ vaulted ceilings

    • Open-concept tracking/mixing space (~1,150 sq ft)

  • New addition includes:

    • Two isolation spaces

    • Kitchenette, bathroom, and lounge/storage area

  • The original hayloft is intact — perfect for synth overdubs or room mics

  • Built by Woodcat Construction, with acoustic design by Matt Azevedo & Acentech

Mar 2025: acoustic treatment

Feb 2025: conduit, wiring, lighting

Jan 2025: floor finishing, paint, reclaimed wood details

12/1/24: Exterior siding is installed

11/27/24: Custom fabricated input panels have arrived

11/22/24: Stone landing and steps are complete

11/13/24: Windows, windows, windows!

11/6/24: The addition now has reclaimed fir flooring and an exterior door

10/23/24: Patchbays and wiring looms are here

9/9/24: Antique heart pine flooring sanded and finished

8/15/24: 3 layers of wallboard are in and plastering is finished

8/14/24: custom studio furniture is being designed and constructed

8/1/24: 1st acoustic measurements of the new room

7/28/24: cabinetry, plumbing and electrical fixtures are in hand, ready for installation

7/15/24: 1st layer of wall board complete in barn. Final wallboarding and plastering complete in addition.

4/24/24: Exterior windows and all doors have arrived.

4/19/24: Regrading and excavation to improve drainage around the site complete.

3/1/24: Strapping is installed. Ready for wall board.

2/11/24: Fixtures have been selected: lighting fixtures, door hardware, cabinetry, sinks, toilets, etc.

2/2/23: Closed cell spray foam insulation underway!

12/12/23: Framing rough-in inspection passed

12/10/23: Structural engineer’s recommendations have been executed. Isolation framing complete!

11/17/23: Plumbing rough-in inspection passed

10/24/23: Electrical infrastructure is in, and passed inspection

9/20/23: Plumbing is in! Framing (standard and isolation) near complete.

6/6/23: Ernesto and René of Woodcat are building the addition platform from LVL and engineered wood I-Joists

5/17/23: Concrete spread footings are poured and curing - Framing next week!

4/21/23: Got the Building Permit today! Monday morning Woodcat begins digging holes for the concrete footings. We’re in motion!!

Barn ⇨ Studio